Change the Property Groups or Values of a Work Order

Before you begin

If you do not have the permission to perform this task, request your administrator to provide the permission using Security.

About this task

You can add a property group or modify the values of properties in a work order only if the corresponding operations are ready or not started.

Procedure

  1. Access the work order that you want to modify.
  2. In the upper-right corner of the page, select , and then select Edit workorder.
    The Edit <work order> page appears, displaying a list of operations in the work order.
  3. Select Properties.
    The Properties workspace appears, displaying a list of property groups assigned to the route appears.
  4. If you want to enter or modify the value of a property:
    1. Expand the group that contains the property whose value you want to enter or modify.
      A list of properties in the group appears.
    2. Enter or modify the value in the VALUE column for each property for which you want to provide a value. The following conditions apply when you provide a value for a property:
      • If a property has been specified as mandatory in the Property Definition application, you must provide a value for the property.
      • The value must be of the same data type as specified in the DATA TYPE column.
  5. If you want to assign a property group to an operation or all operations in the work order:
    1. If you want to assign a property group to an operation, select the operation. If you want to assign a property group to all operations in the work order, select ALL OPERATIONS.
      Note: You can select an operation only if it is not started. You can select ALL OPERATIONS only if at least one of the operations is not started.
    2. Select .
      The Assign Property Group(s) window appears, displaying the property groups that have group definitions.
    3. Select the check boxes corresponding to the property groups that you want to assign.
      Tip: If you want to assign all the property groups, select the check box in the heading.
    4. Select Assign.
  6. Select Save.
    The changes made to the work order are saved.