3.3.2. Move a Carrier into the LOAD Region

About this task

Tip: Follow the same procedure you used to move a block from the SCHEDULE region into the LOAD region.

Clear the Insert check box in the Destination dialog box.

A checked Insert will insert a new empty location at the specified location and put the new item there.

A Move a CARRIER to the LOAD Region
B Confirm that the Carrier Moved

Procedure

  1. Move a CARRIER to the LOAD Region.
  2. Select the Carrier CCAR567 to move to the LOAD region.
  3. Click the Move Item button on the PRT_UI toolbar.

    A Destination dialog box opens.

    Note: Clear the Insert check box in the Destination dialog box.
    A checked Insert will insert a new empty location at the specified location and put the new item there.
  4. Click OK.

    Result: The LOAD_CONV region displays.

  5. Confirm that the Carrier Moved.

    The available carriers should have changed in the LOAD_CONV and LOAD regions.

    The LOAD_CONV region now should have four blocks, not five.

    Blocks that were in Locations 4 and 5 should now be in Locations 3 and 4.

    Both the block and the carrier are now in the LOAD region.

    • CBLK234 is in the LOAD region's Location 1.
    • CCAR567 is in the LOAD region's Location 1.

    The LOAD region was configured to allow 2 items per location.

    Do you remember why you need to clear the Insert check box? Review what happens when you insert or add an item to a region. Check the PRT Region Configuration dialog box; how many locations are in the LOAD region; how many items per location.