Procedure to set the Day Start Time

Procedure

  1. Select Tools on the Action Calendar's menu bar.
  2. Select Setup.

    The Setup dialog box displays.

  3. Enter the following information in the Setup dialog box.
    Day Start Enter a number from 01 to 12
    AM/PM Choose AM or PM from the Menu field.
    Important: Day Start cannot be changed when the project is running. Changing the Day Start requires that the application be exited.