Managed Enterprise Server Project Guidelines
About this task
When a managed project is an Enterprise Server, the Enterprise Server files, ES_*, are included in the managed base configuration.
However, the files will change when the Enterprise project synchronizes with source projects at startup, regardless of its checkout status.
Because of the synchronization, it can take a long time to startup an Enterprise project. Therefore, it is recommended that the changes made by the startup synchronization between the projects get checked into the PCM server.
A recommended approach is as follows.
After points that are marked as Enterprise points have been changed in a source project.