Example: Prioritize Alarm Sounds
You have three projects, each with two Alarm Classes as follows:
Project | Project Priority | Alarm Class 1 | Class 1 Priority | Alarm Class 2 | Class 2 Priority |
---|---|---|---|---|---|
PROJ_A | 3 | ALM_A | 1 | ALM_B | 2 |
PROJ_B | 2 | ALM_A | 1 | ALM_B | 2 |
PROJ_C | 1 | ALM_A | 1 | ALM_B | 2 |
In addition, you currently have one alarm generated for each class in each project.
If you prioritize audio alarms by:
Alarm Class, the alarm order is:
Alarm Sound | Alarm | |
---|---|---|
Order | Project | Class |
1 | PROJ_C | ALM_A |
2 | PROJ_B | ALM_A |
3 | PROJ_A | ALM_A |
4 | PROJ_C | ALM_B |
5 | PROJ_B | ALM_B |
6 | PROJ_A | ALM_B |
Project, the alarm order is:
Alarm Sound | Alarm | |
---|---|---|
Order | Project | Class |
1 | PROJ_C | ALM_A |
2 | PROJ_C | ALM_B |
3 | PROJ_B | ALM_A |
4 | PROJ_B | ALM_B |
5 | PROJ_A | ALM_A |
6 | PROJ_A | ALMB |