Create a Breakpoint

Steps

  1. Access a Production Analysis for which you want to create a breakpoint.

  2. In the left pane, select Production Data.

    The Production Data workspace appears.

    Production Data

  3. On the Production Analysis plot, select the datapoint where you want to insert the breakpoint.

    The Point Tooltip window appears.

    Point Tooltip Window

  4. Select Break.

    GE Digital APM separates the Production Loss region into two shaded regions. The Production Loss Regions pane includes the values for the Sub Reliability Loss regions and the Total Loss region.

    Hint: If you want to remove the breakpoint, select the data point to open the Point Tooltip window, and then select Unbreak.

Copyright © 2018 General Electric Company. All rights reserved.