FIRST_WEEK_DAYS
For | Project Management System |
Purpose | To set the minimum number of days in a week in the current year required to qualify for the first week of the year. This global parameter is used for the $PROJECT.DATE.WEEK system point. |
Value | Number (of days). |
Default Value | 1 |